26. A project manager has just received an extra resource from a functional manager.
Which of the following activities is the BEST to consider for assignment to the resource?
A. Actively A should be assigned because it is within the resource's skillset, has already
been started with three other resources, and has four days of slack
B. Actively B should be assigned because it is not within the resource's skillset, however, it
gives the resource an opportunity to learn a new skill, has not started, and has one day of
slack
C. Actively C should be assigned because it is a task any the resource can do; however, it is
undesirable, needs to be done, has not started, and has three days of slack
D. Actively D should be assigned because it is a new stack, the skillset determination has not
been assessed for the task, it is supposed to start tomorrow, and it has zero slack.