Question:

33. A project manager is developing a network diagram to understand the flow of a project. Which of the following processes is t

33. A project manager is developing a network diagram to understand the flow of a
project. Which of the following processes is the project manager performing?
A. Defining activities
B. Estimating activity resources
C. Developing a schedule
D. Sequencing activities

33. A project manager is developing a network diagram to understand the flow of a project. Which of the following processes is the project manager performing? A. Defining activities B. Estimating activity resources C. Developing a schedule D. Sequencing activities