Question:

20. A project requires that laptops be obtained immediately. The project manager confirmed the existing laptops. Which were used

20. A project requires that laptops be obtained immediately. The project manager
confirmed the existing laptops. Which were used for a previous project, are available, but
authorization is required to use them. Which of the following risk response strategies does
this represent?
A. Exploit
B. Accept
C. Mitigate
D. Transfer

20. A project requires that laptops be obtained immediately. The project manager confirmed the existing laptops. Which were used for a previous project, are available, but authorization is required to use them. Which of the following risk response strategies does this represent? A. Exploit B. Accept C. Mitigate D. Transfer