Question:

48. A project manager is taking over an international project that is in progress and realizes redundant work is being performed

48. A project manager is taking over an international project that is in progress and realizes
redundant work is being performed by teams in different countries. Which of the following
documents would help resolve this issue?
A. Project scope statement
B. Project charter
C. Status report
D. Project communication plan

48. A project manager is taking over an international project that is in progress and realizes redundant work is being performed by teams in different countries. Which of the following documents would help resolve this issue? A. Project scope statement B. Project charter C. Status report D. Project communication plan