Question:
56. Consider the following table of activities A through G in which A is the start node and G is the stop node. Activity Duratio

56. Consider the following table of activities A through G in which A is the start node and G is the stop node. Activity Duration (days)Predecessor A 10 B 20 A C 5 A D 3 B, C E 20 B, C F 4 B, C G 10 D, E, F On a piece of scratch paper, draw the network associated with this table and determine the following. Considering the lengths of all the paths, this project is with maximum slack associated with any one activity of days. 1. Insensitive, 2 2. Sensitive, 2 3. Insensitive, 15 4. Sensitive, 15 5. Insensitive, 17