25. A project scheduler provides a status report that indicates a schedule variance of -$2500. Which of the following does that

25. A project scheduler provides a status report that indicates a schedule variance of -$2500.
Which of the following does that mean?
1. The project is over budget by $2500 worth of work.
2. The project has saved $2500 worth of work.
3. The project has accomplished $2500 worth of work.
4. The project is behind schedule by $2500 worth of work.

25. A project scheduler provides a status report that indicates a schedule variance of -$2500. Which of the following does that mean? 1. The project is over budget by $2500 worth of work. 2. The project has saved $2500 worth of work. 3. The project has accomplished $2500 worth of work. 4. The project is behind schedule by $2500 worth of work.